Ballyrashane Ad Plant
The works package included all formwork operations 1300m2 of a retaining wall to split the site into two levels. Three digestor tank bases at 1950m2 in size with two layers of mesh reinforcment and 200m3 of concrete in each one. The plant was finished off with 5600m2 of new concrete yard.
Wilson Formwork were involved with us in 3 recent projects where their expertise, commitment and ability were of a high standard and contributed to successful projects.